IPEL

deltacque
YEAR OF INSTALLATION/INTERVENTION 1986 (installation and management) 1988 (2° lot)

DELTACQUE typology of action
- Feasibility Study
- Pilot test
- Definitive and Executive project
- Machinery supply
- Assistance to the assembly
- Works supervision in the yard
- Plant start-up
- Laboratory management and supervision of the outlet parameters

Aims of the action
- Obtaining to the proper outlet parameters for the discharge into the river
- Water recovery
- Sludge recovery

Plant capacity
- Hydraulic capacity of the plant: 1.600 m³/day

Waste Water features
Volume m³/day
Inlet: 1.600 Outlet: 1.500
C.O.D. mg/l
Inlet: 10.000 Outlet: 800
B.O.D. mg/l
Inlet: 7.000 Outlet: 300
Sulphides mg/l
Inlet: 100 Outlet: 0,5
Cr 3+ mg/l
Inlet: 50 Outlet: 2
NH4 mg/l
Inlet: 300 Outlet: 0,5
pH
Inlet: 9-10 Outlet: 7-8