TALDOM/OOO SATURN MTK
YEAR OF INSTALLATION/INTERVENTION 2002-2003
DELTACQUE typology of action
- Feasibility Study
- Definitive and Executive project
- Machinery supply
- Works supervision in the yard
- Plant start-up
Aims of the action
- Pre-treatment and treatment of the tanning wastewater
- Biological treatment plant
- Biological sedimentation plant
- Tertiary treatment plant
- Tertiary sedimentation plant
- Sludge treatment plant
- Sulphides recovery plant
- Chrome recovery plant
Plant capacity
- Leather production: 50 Ton/day
- Hydraulic capacity of the plant: 1.200 m³/day
DELTACQUE typology of action
- Feasibility Study
- Definitive and Executive project
- Machinery supply
- Works supervision in the yard
- Plant start-up
Aims of the action
- Pre-treatment and treatment of the tanning wastewater
- Biological treatment plant
- Biological sedimentation plant
- Tertiary treatment plant
- Tertiary sedimentation plant
- Sludge treatment plant
- Sulphides recovery plant
- Chrome recovery plant
Plant capacity
- Leather production: 50 Ton/day
- Hydraulic capacity of the plant: 1.200 m³/day