FATA TANNING Ltd
YEAR OF INSTALLATION/INTERVENTION 2001-2002
DELTACQUE typology of action
- Feasibility Study
- Pilot test
- Definitive and Executive project
- Machinery supply
- Assistance to the assembly
- Works supervision in the yard
- Plant start-up
Aims of the action
- Pre-treatment and treatment of the tanning wastewater
- Biological treatment plant
- Biological sedimentation plant
- Sludge treatment plant
Plant capacity
- Leather production: 25 Ton/day
- Hydraulic capacity of the plant: 800 m³/day
Waste Water features
Volume m³/day
Inlet: 800 Outlet: 736
C.O.D. mg/l
Inlet: 9.000 Outlet: 400
B.O.D. mg/l
Inlet: 4.500 Outlet: 150
Sulphides mg/l
Inlet: 200 Outlet: 2
Cr 3+ mg/l
Inlet: 150 Outlet: 4
NH4 mg/l
Inlet: 250 Outlet: 30
pH
Inlet: 9-10 Outlet: 7-8
DELTACQUE typology of action
- Feasibility Study
- Pilot test
- Definitive and Executive project
- Machinery supply
- Assistance to the assembly
- Works supervision in the yard
- Plant start-up
Aims of the action
- Pre-treatment and treatment of the tanning wastewater
- Biological treatment plant
- Biological sedimentation plant
- Sludge treatment plant
Plant capacity
- Leather production: 25 Ton/day
- Hydraulic capacity of the plant: 800 m³/day
Waste Water features
Volume m³/day
Inlet: 800 Outlet: 736
C.O.D. mg/l
Inlet: 9.000 Outlet: 400
B.O.D. mg/l
Inlet: 4.500 Outlet: 150
Sulphides mg/l
Inlet: 200 Outlet: 2
Cr 3+ mg/l
Inlet: 150 Outlet: 4
NH4 mg/l
Inlet: 250 Outlet: 30
pH
Inlet: 9-10 Outlet: 7-8